Civil Engineering
Architect: Brian O'Connell & Associates Programme - 6 weeks
Engineer: Tygro Consulting Engineers Year - 2005
Value: 85K
Contract Description: installation of 225mm sewer outfall in main roadway; approx 2 - 2.5m deep including manholes, and connection to existing insitu concrete manhole; in a traffic sensitive area; including reinstatement of roadway
Foul Sewer Outfall to Dwelling for Dr G & D Blake at Churchtown, Dublin
Architect: Murray & Associates Programme - 32 weeks
Value: 1.2m Year - 2007
Contract Description: Engineering, management and quantity surveying services for improvement/upgrade works to Chapelizod Park (north & south banks of Liffey) including construction of 4nr fishing stands with gabion baskets and decking, construction of 6 lane running track including specialist surfacing, tree planting, palisade fencing, construction of bitmac surfaced paths to park (4km), landscaping and grass seeding etc.
Architect: Peamount Technical Services Department
Programme - 2 weeks Year - 2007
Contract Description: installation of ducting, cabling and lights to public lighting of roadway within hospital grounds